BMC Fixes Construction Deadlines for Mumbai’s Sion and Belasis Flyovers

Jun 25, 2025

BMC Fixes Construction Deadlines for Mumbai’s Sion and Belasis FlyoversThe Brihanmumbai Municipal Corporation (BMC) has officially announced new deadlines for the completion of two key infrastructure projects in Mumbai – the Sion and Belasis flyovers. These flyovers, which span crucial railway lines, are expected to significantly improve east-west connectivity and reduce traffic bottlenecks in central Mumbai.

Sion Flyover Project – Completion by May 31, 2026 The Sion flyover, which connects the eastern and western parts of the city, is scheduled for completion by May 31, 2026. The southern side foot overbridge (FOB), constructed by the Railways, is expected to be completed by August 31, 2025. Following this, major works like girder installation will begin — north side in November 2025 and south side in January 2026. The western approach road via LBS Marg is nearly complete, while the second underpass work will begin on October 1, 2025. All railway-related components are set to be wrapped up by May 15, 2026.

Belasis Flyover Project – Fast-tracked to December 15, 2025 Initially expected to complete in April 2026, the Belasis flyover is now on a fast-track schedule, with a new deadline of December 15, 2025. It connects Tardeo and Nagpada areas to Mumbai Central station and spans the railway line between Mumbai Central and Grant Road. As part of the project, 13 obstructing structures have been cleared. The installation of 12 girders (each 36 metres long) is targeted for completion by August 10, 2025.

Coordinated Efforts for Timely Completion A progress review meeting held on June 24 at BMC HQ, attended by key BMC and railway officials, focused on ensuring smooth coordination and timely execution of both flyover projects that promise to decongest traffic and enhance urban mobility in Mumbai.

Source: https://www.indiatvnews.com/maharashtra/mumbai-bmc-sets-construction-work-completion-deadline-for-sion-and-belasis-flyovers-check-new-dates-latest-mumbai-news-2025-06-25-996128

Related News

Mysuru’s 105.5 km Peripheral Ring Road Project Enters Land-Acquisition Phase: MDA Prepares for Major Urban Expansion

Mysuru’s 105.5 km Peripheral Ring Road Project Enters Land-Acquisition Phase: MDA Prepares for Major Urban Expansion

The Mysuru Development Authority (MDA) begins land acquisition efforts for the 105.5 km Peripheral Ring Road (PRR), planning a 200-foot wide, six-lane corridor with service roads and surrounding township over 27,500 acres to decongest the city and catalyze regional growth.

11/17/2025
Jinkushal Industries Secures $5 Million Repeat Export Order for HexL 420X Backhoe Loaders

Jinkushal Industries Secures $5 Million Repeat Export Order for HexL 420X Backhoe Loaders

Jinkushal Industries (JKIPL) wins a USD 5 million repeat export order from North America for 100 HexL 420X Backhoe Loaders, marking a key milestone in India’s export-led construction equipment growth story.

11/12/2025
BMC, MRIDC to Build Rs 805-Crore Cable-Stayed Y-Bridge Flyover in Byculla

BMC, MRIDC to Build Rs 805-Crore Cable-Stayed Y-Bridge Flyover in Byculla

The BMC and MRIDC have invited bids for a Rs 805-crore cable-stayed flyover linking the historic Y-Bridge in Byculla with the JJ Flyover, aimed at decongesting South Mumbai’s traffic corridors

10/29/2025
Adani’s ITD Cementation Wins ₹1,644 Crore Pune Metro Contract for Swargate–Katraj Underground Line

Adani’s ITD Cementation Wins ₹1,644 Crore Pune Metro Contract for Swargate–Katraj Underground Line

Maha-Metro has awarded a ₹1,644 crore contract to Adani Group’s ITD Cementation India Ltd for the 5.46 km Swargate–Katraj underground Pune Metro stretch. The project will include three stations and boost connectivity in southern Pune.

10/27/2025
KPIL Order Inflows Near ₹15,000 Crore in FY26, Up 25% YoY

KPIL Order Inflows Near ₹15,000 Crore in FY26, Up 25% YoY

KPIL reports strong order inflows nearing ₹15,000 crore in FY26, marking 25% YoY growth driven by robust demand in power transmission and building projects.

10/24/2025